All parts of sections 4, 5, 6 and 8 of ISO 9001 apply in their entirety
to all organisations, and there are no circumstances under which an
organisation may claim exclusion to any parts of these sections. Exclusions to parts of section 7 can be considered, but this
is only permissible where the requirement does not apply to the organisation (refer to clause 1.2 of ISO 9001).
That is, if the organisation has no design function, there is no design work to
be controlled or audited, so it is permissible to exclude clause 7.3 from the
scope of certification. It is not permissible to exclude a design function from
scope because it is very poor and you would rather it wasn’t assessed
The following table summarises the circumstances under which an organisation may consider excluding a part of section 7 from the scope of certification. The most common exclusions are clauses 7.3, 7.6, 7.5.2 and 7.5.4:
|
ISO 9001 Clause |
Justification for exclusion |
|
7.1 Planning of product realisation |
It is hard to contemplate a situation where an organisation would be able to justify this exclusion. The clause covers production planning or, for a service provider, planning of service delivery. Consequently it would encompass scheduling of work, rotas, shifts, organising deliveries, ordering of materials, holiday cover and more Effectively a company would be asking to be excluded from the “P” of PDCA. PDCA is fundamental and underpinning principle of ISO 9001 – this exclusion isn’t going to happen, so don’t even go there |
|
7.2 Customer related processes |
All organisations will have processes with inputs, activities and outputs, and there will always be a customer at one end or, more commonly, at both ends. This could be an end-consumer or end-user, or it could be an internal customer, but your processes must be working for the benefit or convenience of someone. Again this part of the standard would be impossible to exclude and reasonably justify |
|
7.3 Design and development |
Many organisations don’t have a
design function. They may This is the most common exclusion to the scope of certification |
|
7.4 Purchasing |
This is a rare exclusion but it
is feasible. Although it covers the selection of suppliers, and you may think
that everyone must have some suppliers, there is not always any economic
benefit in applying any sort of selection and approval controls to them. For
example if an organisation only buys standard catalogue or boxed items
(stationery, manuals, off-the-shelf hardware and software for example) and it
does not use sub-contractors or agency staff, then an exclusion to 7.4 is a
possibility
|
|
7.5.1 Control of production and service provision |
The scope of this sub-clause is very broad. It includes the provision of workplace instructions, product specifications, equipment, and monitoring activities. An attempt to exclude this clause would be tantamount to asking to be excused from controlling activities full stop. Again, don’t go there |
|
7.5.2 Validation of processes for production and service provision |
At first sight this may look
like another unthinkable contender for consideration, but it is in fact a
fairly common candidate. A common misconception is that this clause requires
an organisation to exercise generic process control across its operational
activities, but its application is in fact much, much narrower than that. The
clause requires an organisation to establish process validation methods only
for those processes whose outputs cannot be verified by subsequent monitoring
or measurement. ISO 9001:1994 used to call them “Special Processes”. Think
about that for a moment. Many companies only produce outputs that CAN be
tested, they don’t have any of these so called special processes, so they can
exclude this clause as it is inapplicable to them It applies when the output can only
be fully tested in a destructive way (e.g. a weld) or when it is impractical to test, for example there may simply be no
time to test (e.g. in a radiological treatment agent with a half-life of 2
hours) In those cases, because we can't test the output, we have to have absolute faith in the process, so we need additional process controls and validation. It is in these circumstances that clause 7.5.2 applies |
|
7.5.3 Traceability |
Manufacturers of high volume,
low value, low risk items (e.g. |
|
7.5.4 Customer property |
Many manufacturers and service
providers do not hold any |
|
7.5.5 Preservation of product |
This clause requires the “product” be protected from damage or deterioration. If an organisation provides a service such as “advice” then there is no potential for the output to “spoil” in any way and this clause may well be excluded |
|
7.6 Control of monitoring and measuring equipment |
Many service providers don’t
use measuring devices that require |